A construction project consists of four activities. The quantity of work, manpower requirement, and the productivity of the activities are listed in the table below. The interrelationship between the activities are also mentioned in the table. The construction project will start on January 29. Assume no holidays for the entire duration of the project. The project will finish on February \underline{\hspace{1cm}} [mention date in number].\[\begin{array}{|c|c|c|c|c|} \hline Activity & Quantity (cu.m) & Manpower (persons) & Productivity (cu.m/man-day) & Immediate Successor Activity \\ \hline \text{A} & \text{96} & \text{8} & \text{3} & \text{C} \\ \hline \text{B} & \text{252} & \text{7} & \text{4} & \text{C \} & \text{D} \\ \hline \text{C} & \text{275} & \text{5} & \text{5} & \text{Nil} \\ \hline \text{D} & \text{126} & \text{6} & \text{3} & \text{Nil} \\ \hline \end{array}\]