Step 1: Calculate duration of each activity.
Formula:
\[
\text{Duration} = \frac{\text{Quantity}}{\text{Manpower} \times \text{Productivity}}
\]
- Activity A: \( \frac{96}{8 \times 3} = \frac{96}{24} = 4 \; \text{days} \)
- Activity B: \( \frac{252}{7 \times 4} = \frac{252}{28} = 9 \; \text{days} \)
- Activity C: \( \frac{275}{5 \times 5} = \frac{275}{25} = 11 \; \text{days} \)
- Activity D: \( \frac{126}{6 \times 3} = \frac{126}{18} = 7 \; \text{days} \)
Step 2: Dependencies.
- A → C
- B → C \& D
So:
- C can start only after both A and B are completed.
- D can start only after B is completed.
Step 3: Timeline.
- Start date = Jan 29.
- A: 4 days → finishes Feb 1.
- B: 9 days → finishes Feb 6.
- C: Starts after A and B = Feb 6, runs 11 days → finishes Feb 16.
- D: Starts after B = Feb 6, runs 7 days → finishes Feb 12.
Step 4: Project completion.
Since the project finishes when the last activity (C or D) finishes, completion = Feb 16.
Final Answer: \[ \boxed{\text{February 16}} \]
Fish : Shoal :: Lion : _________
Select the correct option to complete the analogy.
P and Q play chess frequently against each other. Of these matches, P has won 80% of the matches, drawn 15% of the matches, and lost 5% of the matches.
If they play 3 more matches, what is the probability of P winning exactly 2 of these 3 matches?
The given figure is reflected about the horizontal dashed line and then rotated clockwise by 90° about an axis perpendicular to the plane of the figure.
Which one of the following options correctly shows the resultant figure?
Note: The figures shown are representative