>
Exams
>
Construction and Management
>
Estimation and Specification
>
the optimistic most likely duration and the pessim
Question:
The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
CUET (PG) - 2023
CUET (PG)
Updated On:
Mar 21, 2024
11.67 Months
10.67 Months
9.67 Months
8.67 Months
Hide Solution
Verified By Collegedunia
The Correct Option is
C
Solution and Explanation
The correct answer is (C) : 9.67 Months.
Download Solution in PDF
Was this answer helpful?
0
0
Top Questions on Estimation and Specification
A primary school is having 8 class rooms, each having internal dimensions of 15m × 10m × 4m (height). Only the internal walls of all the class rooms are proposed to be painted. Assume a deduction of 10% internal wall area due to doors, windows etc. The specification suggests two coats of paint application. The spreading rates of the selected paint during base coat and finish coat are 4.5 l/sq.m and 2.5 l/sq.m respectively. The amount of paint (in liters) required for the job will be \underline{\hspace{1cm}}.
GATE AR - 2023
Construction and Management
Estimation and Specification
View Solution
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
CUET (PG) - 2023
Construction and Management
Estimation and Specification
View Solution
Given the dimensions of a room, tile sizes, door size, and the height of skirting, calculate the number of ceramic tiles required for internal flooring and skirting.
GATE AR - 2021
Construction and Management
Estimation and Specification
View Solution
View All
Questions Asked in CUET PG exam
The following table shows the total number of people who were stuck in traffic jam while going to their office on working days of a week due to construction of a flyover. Table also shows the ratio of male to female among them. Find the average number of females who were stuck in traffic on working days.
CUET (PG) - 2025
Table
View Solution
Study the following table and answer the question that follows. If the population of state B is 42,00,000 and the population of state C is 32,00,000, then what is the sum of number of females below poverty line in state B and number of males below poverty line in state C?
CUET (PG) - 2025
Table
View Solution
The following table shows the total number of people who were stuck in traffic jam while going to their office on working days of a week due to construction of a flyover. Table also shows the ratio of male to female among them. If 30% males on Tuesday and 60% males on Wednesday reached their office on regular time of the office, then how many males got late on Tuesday and Wednesday taken together?
CUET (PG) - 2025
Table
View Solution
Correct the following sentence by replacing the underlined word from the given options:
Chanakya, also known as Kautilya the strategist, lived ............ the reign of Chandragupta Maurya.
CUET (PG) - 2025
Prepositions
View Solution
Study the following table and answer the question that follows. The given table shows the percentage population of three states A, B and C below poverty line and the ratio of males and females as per poverty line. If the total population of state A is 51,00,000, then what is the number of females above the poverty line in state A?
CUET (PG) - 2025
Table
View Solution
View More Questions