Question:

The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -

Updated On: Mar 21, 2024
  • 11.67 Months
  • 10.67 Months
  • 9.67 Months
  • 8.67 Months
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

The correct answer is (C) : 9.67 Months.
Was this answer helpful?
0
0