Question:

The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -

Updated On: Mar 21, 2024
  • 6 months
  • 6.5 months
  • 7 months
  • 7.5 months
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct answer is (B) : 6.5 months.
Was this answer helpful?
0
0