>
Exams
>
Construction and Management
>
Estimation and Specification
>
the optimistic most likely duration and the pessim
Question:
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
CUET (PG) - 2023
CUET (PG)
Updated On:
Mar 21, 2024
6 months
6.5 months
7 months
7.5 months
Hide Solution
Verified By Collegedunia
The Correct Option is
B
Solution and Explanation
The correct answer is (B) : 6.5 months.
Download Solution in PDF
Was this answer helpful?
0
0
Top Questions on Estimation and Specification
The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
CUET (PG) - 2023
Construction and Management
Estimation and Specification
View Solution
View All
Questions Asked in CUET PG exam
What is the correct verb form: He, as well as his friends, ?
CUET (PG) - 2025
Verbs
View Solution
Which preposition is correct: Chanakya lived ?
CUET (PG) - 2025
Prepositions
View Solution
Identify the possessive noun: My office car is parked elsewhere.
CUET (PG) - 2025
Nouns
View Solution
Which tense is appropriate: How did Saira ?
CUET (PG) - 2025
Tenses
View Solution
Complete the sentence: There is a growing synthesis between humanism and ?
CUET (PG) - 2025
Sentence Completion
View Solution
View More Questions