Question:

The network diagram of a construction project is shown in the following Figure. The duration of each activity, in days, and the early start time of the project are denoted in the diagram. The total project duration along the critical path, in days, is _____(in integer).
The network diagram of a construction project is shown in the following Figure. The duration of each activity,

Updated On: Jul 9, 2024
Hide Solution
collegedunia
Verified By Collegedunia

Correct Answer: 18

Solution and Explanation

The correct answer is :18
Was this answer helpful?
0
0

Questions Asked in GATE AR exam

View More Questions