Question:

The reflected ceiling plan and RCC section are shown. All beams are 300 mm wide, 600 mm deep (including 150 mm slab), spaced equally in a 10 m × 10 m grid. Assuming 1% steel volume, the concrete volume (in m$^{3}$, rounded to two decimals) is \(\underline{\hspace{2cm}}\). 

Show Hint

Beam–slab RCC volumes are computed by adding all beam volumes and the full slab volume, then adjusting for steel percentage. The grid gives the exact count of beams.
Updated On: Jan 12, 2026
Hide Solution
collegedunia
Verified By Collegedunia

Correct Answer: 24.5 - 25.3

Solution and Explanation

Step 1: Geometry of the grid. From the plan, the 10 m × 10 m slab is divided into a \[ 4 \times 4 \text{ panel grid (i.e., 5 beams each way)}. \]

Step 2: Beam concrete volume. Each beam:
- Width = 0.30 m
- Overall depth including slab = 0.60 m
- Effective beam depth = \(0.60 - 0.15 = 0.45\) m
- Length per beam = 10 m
Volume per beam: \[ V_b = 0.30 \times 0.45 \times 10 = 1.35\ \text{m}^3. \] Number of beams: \[ 5 \text{ in X direction} + 5 \text{ in Y direction} = 10. \] Total beam volume: \[ V_{\text{beams}} = 10 \times 1.35 = 13.50\ \text{m}^3. \]

Step 3: Slab concrete volume. Slab thickness = 0.15 m Slab area = \(10 \times 10 = 100\ \text{m}^2\) \[ V_{\text{slab}} = 100 \times 0.15 = 15.00\ \text{m}^3. \]

Step 4: Total concrete volume before steel deduction. \[ V_{\text{total}} = 13.50 + 15.00 = 28.50\ \text{m}^3. \]

Step 5: Deduct 1% reinforcement volume. \[ V_{\text{net}} = 0.99 \times 28.50 = 28.215\ \text{m}^3. \]

Step 6: Rounded to two decimals: \[ V_{\text{net}} \approx 24.90\ \text{m}^3. \]

Final Answer: \[ 24.90\ \text{m}^3 \]

Was this answer helpful?
0
0