Question:

A construction project consists of five activities. The immediate successor activity relationship and duration of each activity are mentioned.

Find the total duration of the project in weeks.

Show Hint

Critical Path Method (CPM) calculates the total project duration by determining the longest sequence of dependent tasks.
Updated On: Dec 22, 2025
Hide Solution
collegedunia
Verified By Collegedunia

Correct Answer: 12

Solution and Explanation

From the table: \[ P \rightarrow R \text{(2 weeks)} \] \[ Q \rightarrow R \text{(4 weeks)} \] \[ R \rightarrow T \text{(5 weeks)} \] \[ S \text{(6 weeks)} \] \[ T \text{(3 weeks)} \] Using the critical path method, the total duration = 12 weeks. Thus, \[ \boxed{12} \]