The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
CUET (PG) - 2023
CUET (PG)
Construction and Management
Estimation and Specification
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
CUET (PG) - 2023
CUET (PG)
Construction and Management
Estimation and Specification