The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
  • CUET (PG) - 2023
  • CUET (PG)
  • Construction and Management
  • Estimation and Specification
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
  • CUET (PG) - 2023
  • CUET (PG)
  • Construction and Management
  • Estimation and Specification
For the construction of retaining structures, the type of concrete mix to be used is
  • CUET (PG) - 2023