Question:

If 'A' and 'B' can do a piece of work in 8 days, while 'A' alone can do it in 12 days. In how many days can 'B' alone do the same work?

Show Hint

To find the work done by one worker when two workers' combined work rate is given, use: \[ \text{Work rate of B} = \text{Work rate of A and B together} - \text{Work rate of A} \]
Updated On: Mar 25, 2025
  • 24 days
  • 12 days
  • 16 days
  • 20 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Given: - A and B together complete the work in 8 days. - A alone completes the work in 12 days. Step 1: Work done per day by A: \[ \frac{1}{12} \] Step 2: Work done per day by A and B together: \[ \frac{1}{8} \] Step 3: Work done per day by B: \[ \frac{1}{8} - \frac{1}{12} \] Taking LCM of 8 and 12, which is 24: \[ \frac{3}{24} - \frac{2}{24} = \frac{1}{24} \]
Thus, B alone takes 24 days to complete the work.
Was this answer helpful?
0
0