45 men can complete a work in 16 days. After working for some days, 30 more men joined the work. As a result, work now finished in 6 days. How many days after the commencement of the work did the 30 persons join?
Show Hint
When dealing with work problems, use the concept of man-days to relate work, workers, and time.
Let the number of days the 45 men worked before the 30 men joined be \( x \).
The total work required is:
\[
\text{Total Work} = 45 \times 16 = 720 \, \text{man-days}
\]
After \( x \) days, 30 more men joined, making the total number of men \( 75 \). The remaining work is:
\[
\text{Remaining Work} = 720 - 45x
\]
The remaining work is completed in 6 days by 75 men, so:
\[
\text{Remaining Work} = 75 \times 6 = 450 \, \text{man-days}
\]
Now, equate the remaining work:
\[
720 - 45x = 450
\]
\[
45x = 270
\]
\[
x = 6
\]
Thus, 30 men joined after 12 days.