Let:
- Work done by 1 man per day = \( M \)
- Work done by 1 boy per day = \( B \)
Given:
1. 2 men and 5 boys finish the work in 4 days:
\[
4(2M + 5B) = 1
\]
\[
2M + 5B = \frac{1}{4}
\]
2. 3 men and 6 boys finish the work in 3 days:
\[
3(3M + 6B) = 1
\]
\[
3M + 6B = \frac{1}{3}
\]
Solving:
Multiply the first equation by 3 and the second by 2:
\[
6M + 15B = \frac{3}{4}
\]
\[
6M + 12B = \frac{2}{3}
\]
Subtracting:
\[
(6M + 15B) - (6M + 12B) = \frac{3}{4} - \frac{2}{3}
\]
\[
3B = \frac{9}{12} - \frac{8}{12} = \frac{1}{12}
\]
\[
B = \frac{1}{36}
\]
Substituting into \( 2M + 5B = \frac{1}{4} \):
\[
2M + \frac{5}{36} = \frac{1}{4}
\]
\[
2M = \frac{9}{36} - \frac{5}{36} = \frac{4}{36}
\]
\[
M = \frac{1}{18}
\]
Thus, one man alone will take:
\[
\frac{1}{\frac{1}{18}} = 18 \text{ days}
\]
Thus, the correct answer is 18 days.