Step 1: Determine Gauri’s work rate.
Gauri completes 1 work in 3 hours.
So, Gauri’s rate of work \( = \frac{1}{3} \) work per hour.
Step 2: Determine Sita’s work rate using efficiency relation.
Gauri is 2 times more efficient than Sita.
So, Sita’s efficiency (and work rate) is half of Gauri’s.
Sita’s rate of work \( = \frac{1}{6} \) work per hour.
Step 3: Calculate their combined work rate.
Combined rate of work
\[
= \frac{1}{3} + \frac{1}{6} = \frac{1}{2}
\]
work per hour.
Step 4: Consider the size of work to be completed.
The work to be done is 2 times the original work.
So, total work \( = 2 \) units.
Step 5: Calculate the time required.
\[
\text{Time} = \frac{\text{Total work}}{\text{Combined rate}} = \frac{2}{\frac{1}{2}} = 4 \text{ hours}
\]
Step 6: Conclusion.
If Gauri and Sita work together, they will complete the work in 4 hours.