Step 1: Identify all possible paths from the start event to the end event.
We need to trace all the sequences of activities from node 1 (Start event) to node 6 (End event).
The possible paths are:
1. 1 $\rightarrow$ 2 $\rightarrow$ 3 $\rightarrow$ 5 $\rightarrow$ 6 (Activities A-B-D-F)
2. 1 $\rightarrow$ 2 $\rightarrow$ 4 $\rightarrow$ 5 $\rightarrow$ 6 (Activities A-C-E-F)
Step 2: Calculate the total duration for each path by summing the time estimates of the activities along that path.
For Path 1 (A-B-D-F):
Duration = Time(A) + Time(B) + Time(D) + Time(F)
Duration = 3 days + 5 days + 10 days + 4 days = 22 days
For Path 2 (A-C-E-F):
Duration = Time(A) + Time(C) + Time(E) + Time(F)
Duration = 3 days + 7 days + 5 days + 4 days = 19 days
Step 3: Identify the critical path.
The critical path is the longest path in the network diagram, as it determines the minimum project completion time. The path with the maximum duration is the critical path.
Comparing the durations of the two paths:
Path 1: 22 days
Path 2: 19 days
The longest duration is 22 days, which corresponds to Path 1 (A-B-D-F). Therefore, the critical path is 1 $\rightarrow$ 2 $\rightarrow$ 3 $\rightarrow$ 5 $\rightarrow$ 6.
Step 4: Determine the project completion time.
The project completion time based on the critical path is the duration of the critical path. In this case, it is 22 days.