Question:

Earliest finish of an activity is always:

Show Hint

In project scheduling, the earliest finish is always less than or equal to the earliest event of the succeeding node.
Updated On: Sep 24, 2025
  • Less than earliest event of the following node
  • Greater than earliest event of the following node
  • Less than or equal to earliest event of the following node
  • Greater than or equal to earliest event of the following node
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Understanding the Concept of Earliest Finish.
The earliest finish of an activity is the earliest time that the activity can be completed considering all its predecessors. It must be less than or equal to the earliest event of the following node because the activity cannot finish before the following event starts.

Step 2: Conclusion.
Thus, the correct answer is (3): the earliest finish is less than or equal to the earliest event of the following node.

Final Answer: \[ \boxed{3. \, \text{Less than or equal to the earliest event of the following node.}} \]