Select the correct sequence of steps of controlling process which are given below.
A. Analysing deviations
B. Measurement of actual performance
C. Setting performance standards
D. Comparison of actual performance with standards
E. Taking corrective action
Choose the correct answer from the options given below:

Updated On: Mar 12, 2025
  • B, C, D, A, E
  • C, B, D, A, E
  • C. B, D, E, A
  • C. B, E, A, D
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is (B): C, B, D, A, E