Identify the correct sequence of first 5 steps of the planning process:
(A) Developing premises
(B) Identifying alternative courses of action
(C) Evaluating alternative courses
(D) Setting objectives
(E) Selecting an alternative
Choose the correct answer from the options given below:

Show Hint

Understanding the sequence of planning steps is crucial for effective decision-making in management. Remember, it starts with defining objectives and ends with choosing the best course of action.
Updated On: Apr 24, 2025
  • C, D, B, E, A
  • D, A, B, C, E
  • C, E, D, A, B
  • A, D, B, C, E
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The first five steps of the planning process are generally as follows:
1. Developing premises (A)
2. Identifying alternative courses of action (B)
3. Evaluating alternative courses (C)
4. Setting objectives (D)
5. Selecting an alternative (E)
Thus, the correct sequence is: C, D, B, E, A.