Question:

B can do a work in 48 days. If A starts the work and after 10 days he leaves, then B alone finishes the remaining work in 42 days. In how many days A and B together will finish the work?

Show Hint

To find the time taken when two people are working together, first calculate their individual rates of work and then sum the rates.
Updated On: Feb 16, 2025
  • 30
  • 25
  • 35
  • 28
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Let the total work be \( W \). - B can complete the work in 48 days, so B’s rate of work is: \[ \text{B’s rate} = \frac{W}{48} \] - In the first 10 days, A works alone. Let A’s rate of work be \( \frac{W}{a} \), where \( a \) is the number of days A would take to complete the work alone. The work done by A in the first 10 days is: \[ \text{Work done by A} = 10 \times \frac{W}{a} = \frac{10W}{a} \] After A leaves, B finishes the remaining work in 42 days, so the work done by B in 42 days is: \[ \text{Work done by B} = 42 \times \frac{W}{48} = \frac{7W}{8} \] The total work is \( W \), so the remaining work after 10 days is: \[ W - \frac{10W}{a} = \frac{7W}{8} \] Solving for \( a \): \[ W - \frac{10W}{a} = \frac{7W}{8} \quad \Rightarrow \quad \frac{10W}{a} = \frac{W}{8} \quad \Rightarrow \quad a = 80 \] Thus, A can complete the work in 80 days. Now, we calculate the time taken for A and B to complete the work together. Their combined rate is: \[ \text{Combined rate} = \frac{W}{80} + \frac{W}{48} = \frac{48W + 80W}{80 \times 48} = \frac{128W}{3840} = \frac{W}{30} \] Thus, A and B together will complete the work in \( \boxed{30} \) days.
Was this answer helpful?
0
0