Question:

A contractor estimates that 3 persons could rewire Jasminder's house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?

Updated On: Dec 5, 2023
Hide Solution
collegedunia
Verified By Collegedunia

Solution and Explanation

Let the number of days required by 4 persons to complete the job be x.
The following table is obtained. 

Number of days4x
Number of persons34

If the number of persons is more, then it will take lesser time to complete the job.
Hence, the number of days and the number of persons required to complete the job are inversely proportional to each other.
Therefore, \(4 × 3 = x × 4\)
\(x = \frac{4 × 3}{4}\)
Thus, the number of days required to complete the job is 3.

Was this answer helpful?