Question:

The table shows the activities and their durations and dependencies in a project.
ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K
The total duration (in days) of the project is ______ (in integer).

Updated On: Jan 2, 2025
Hide Solution
collegedunia
Verified By Collegedunia

Correct Answer: 30

Solution and Explanation

The correct answer is 30.
Was this answer helpful?
0
3

Top Questions on Construction Management

View More Questions

Questions Asked in GATE CE exam

View More Questions