Question:

Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The 'schedule variance' for the project is

Updated On: Jul 18, 2024
  • (-)Rs. 50
  • (-)50 days
  • (+)Rs. 50
  • (+)50 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct option is (A) : (-)Rs. 50.