Question:

The following figure shows the arrangement of formwork for casting a cantilever RC beam.
cantilever RC beam.
The correct sequence of removing the Shores/Props is:

Updated On: Jul 17, 2024
  • \(S1 \mapsto S2 \mapsto S3 \mapsto S4 \mapsto S5\)
  • \(S5 \mapsto S4 \mapsto S3 \mapsto S2 \mapsto S1\)
  • \(S3 \mapsto S2 \mapsto S4 \mapsto S1 \mapsto S5\)
  • \(S3 \mapsto S4 \mapsto S2 \mapsto S5 \mapsto S1\)
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is (2) :\(S5 \mapsto S4 \mapsto S3 \mapsto S2 \mapsto S1\)