Question:

The standard time for completing a job on a machine is 10 minutes. Number of machines available is 5, each machine is available for 300 hours/month, and average machine utilization is 80%. The maximum number of jobs that can be produced in a month is ................. (in integer).

Show Hint

To calculate the maximum number of jobs, convert the job time into hours, multiply by machine hours available, and adjust for machine utilization.
Updated On: Sep 4, 2025
  • 7200
  • 6800
  • 8000
  • 7500
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

- Total available machine hours per month = 5 machines \(\times\) 300 hours/machine = 1500 hours.
- Given that the machine utilization is 80%, the effective machine hours = \(1500 \times 0.8 = 1200\) hours.
- Each job takes 10 minutes, which is \(\frac{10}{60} = \frac{1}{6}\) hours.
- The number of jobs that can be produced in a month is: \[ \text{Number of jobs} = \frac{1200}{\frac{1}{6}} = 1200 \times 6 = 7200. \]