Question:

The minimum time delay between initiation of two independent memory operations is called

Show Hint

Cycle time is a key parameter for determining the speed of memory operations.
Updated On: May 3, 2025
  • Cycle time
  • Access time
  • Transfer time
  • Latency
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The minimum time delay between the initiation of two independent memory operations is referred to as the "Cycle time". It defines the interval between consecutive operations.
Thus, the correct answer is \( \text{Cycle time} \).