Consider the statements P and Q.
P: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client's Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?

Updated On: Jul 17, 2024
  • Both P and Q are TRUE
  • P is TRUE and Q is FALSE
  • Both P and Q are FALSE
  • P is FALSE and Q is TRUE
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct option is (A) :Both P and Q are TRUE