To solve this problem, let's denote the work done by Stuart, Jack, and Leo per day as \( S \), \( J \), and \( L \) respectively. We have three equations based on the given information:
We want to find the combined work rate of Stuart and Jack to compute how long they take to finish the remaining work. First, add the three equations:
\((S + J) + (J + L) + (S + L) = \frac{1}{10} + \frac{1}{15} + \frac{1}{12}\)
Which simplifies to:
\(2S + 2J + 2L = \frac{1}{10} + \frac{1}{15} + \frac{1}{12}\)
Combine like terms:
\(2(S + J + L) = \frac{1}{10} + \frac{1}{15} + \frac{1}{12}\)
Find a common denominator (60):
\(2(S + J + L) = \frac{6}{60} + \frac{4}{60} + \frac{5}{60} = \frac{15}{60} = \frac{1}{4}\)
\((S + J + L) = \frac{1}{8}\)
Now knowing the combined rate of all three, calculate \( S + J \):
\(S + J = (S + J + L) - L = \frac{1}{8} - L\)
From the equation \( J + L = \frac{1}{15} \), solve for \( L \):
\(L = \frac{1}{15} - J\)
Substitute \( L \) in the equation \( S + L = \frac{1}{12} \) to solve:
\(S + \left(\frac{1}{15} - J\right) = \frac{1}{12}\)
Simplify and solve for \( J \) and substitute back for \( S + J \). But realizing the complexity of simplifying directly, observe they worked together for 2 days, leaving:
Work done in 2 days: \(2 \times \frac{1}{8} = \frac{1}{4}\)
Remaining work: \(1 - \frac{1}{4} = \frac{3}{4}\)
Stuart and Jack's combined rate: \(S + J = \frac{1}{10}\)
Time required for the remaining work:
\(\text{Time} = \frac{\text{Remaining work}}{\text{Combined rate}} = \frac{3/4}{1/10} = \frac{3/4} \times \frac{10}{1} = 7.5\)
Thus, Stuart and Jack will take 7.5 days to finish the rest of the work.
Find the missing code:
L1#1O2~2, J2#2Q3~3, _______, F4#4U5~5, D5#5W6~6