Question:

A can do a work in 12 days and B in 18 days. if they start work together, and after 2 days B leaves then how many days will it take for the work to get completed?

Show Hint

The LCM method is often faster and less prone to calculation errors than the fraction method for Time and Work problems.
Updated On: Dec 8, 2025
  • 7
  • 8.66
  • 9
  • 10.66
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Step 1: Understanding the Question:
A and B work together for 2 days, after which B leaves. A completes the rest of the work alone. We need to find the total time taken to complete the entire work.
Step 2: Key Formula or Approach:
We will use the LCM method to find the total work and individual efficiencies. - Total Work = LCM of individual times. - Efficiency = Total Work / Time taken.
Step 3: Detailed Explanation:
Time taken by A = 12 days.
Time taken by B = 18 days.
Let the total work be the LCM of 12 and 18, which is 36 units.
- A's efficiency (work per day) = 36 / 12 = 3 units/day. - B's efficiency (work per day) = 36 / 18 = 2 units/day.
Combined efficiency of A and B = 3 + 2 = 5 units/day.
They work together for 2 days. Work done in 2 days = Combined efficiency \(\times\) 2 = 5 \(\times\) 2 = 10 units.
Remaining work = Total work - Work done = 36 - 10 = 26 units.
B leaves, and A completes the remaining 26 units of work alone.
Time taken by A to finish the remaining work = Remaining work / A's efficiency Time = 26 / 3 = 8.66 days.
The question asks for the total number of days for the work to get completed.
Total days = Days they worked together + Days A worked alone Total days = 2 + 8.66 = 10.66 days.
Step 4: Final Answer:
The total time taken for the work to get completed is 10.66 days.
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions