Slack time in PERT Analysis

Updated On: Mar 21, 2024
  • Can never be greater than zero
  • Is always zero for critical activities
  • Can never be less than zero
  • Is minimum for critical events
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

The correct option is(D): Is minimum for critical events