Question:

Given below are two statements:
Statement - I: PERT is most suitable for research and development type of projects as it account for uncertainties involved in estimation of time estimates.
Statement - II: Acritical path, method is suitable for repetitive type of projects for example construction projects.
In the light of the above statements, choose the correct answer from the options given below :

Updated On: Mar 21, 2024
  • Both Statement I and Statement II are true.
  • Both Statement I and Statement II are false.
  • Statement I is true but Statement II is false.
  • Statement I is false but Statement II is true.
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct answer is (A) : Both Statement I and Statement II are true..
Was this answer helpful?
0
0