Question:

In PERT technique, the time estimate of activities and probability of their concurrence follows :

Updated On: Mar 21, 2024
  • Normal distribution curve
  • β-distribution curve
  • Poisson distribution curve
  • Binomial distribution curve
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct answer is (B) : β-distribution curve.