Let's denote the work rate of Rahul as \(R\) work/hour and the work rate of Gautam as \(G\) work/hour.
1) When both started together at 9 AM:
The total time they worked together was 8 hours (from 9 AM to 5 PM). They would have finished the work in 7.5 hours (30 minutes earlier). So, their combined work rate when they started together would be:
\(Total \ Work = (R + G) \times 7.5\)
2) On the day Rahul started at 9 AM and Gautam joined him 2 hours later:
Rahul worked for 2 hours alone, and then they worked together for the next 6 hours (from 11 AM to 5 PM). This gives:
\(Total \ Work = 2R + 6(R + G)\)
Since the total work done in both scenarios is the same, we can equate the two expressions:
\(2R + 6(R + G) = 7.5(R + G)\)
Expanding and simplifying:
\(2R + 6R + 6G = 7.5R + 7.5G\)
\(8R + 6G = 7.5R + 7.5G\)
\(0.5R = 1.5G\)
\(R = 3G\)
Now, let's use the combined work rate from the first scenario:
\(Total \ Work = (R + G) \times 7.5\)
Using the relationship \(R = 3G\), we get:
\(Total \ Work = (3G + G) \times 7.5\)
\(Total \ Work = 4G \times 7.5\)
\(Total \ Work = 30G\)
Now, using this total work with Rahul's individual work rate for the time he worked alone:
\(2R = 2(3G) = 6G\)
Subtracting this from the total work to get the work done by both together:
\(30G - 6G = 24G\)
This means that both of them, working together for 6 hours, did \(24G\) of the work:
\(6(R + G) = 24G\) Using \(R = 3G\):
\(6(4G) = 24G\)
The relationship holds true.
Now, to find the time Rahul would take to complete the entire work by himself:
Using \(R = 3G\):
\(Total \ Work = 30G\)
If Rahul does the entire work:
\(Time \ for \ Rahul = \frac{Total \ Work}{R} = \frac{30G}{3G} = 10 \ hours\)
Rahul would take 10 hours to complete the work by himself.
Let R be the percentage of Rahul's work completed in an hour.
and G represent the portion of Gautam's work completed in an hour.
At first, Rahul works eight hours a day, from 9 AM to 5 PM, while Gautam works two hours less.
8R + 6G equals a single work unit.
They end thirty minutes sooner if they start at the same time and end at 4:30 PM (7.5 hours) if they start at 9 AM.
\(7.5R + 7.5G\) equals a single work unit.
\(7.5R + 7.5G = 8R + 6G\)
\(0.5R = 1.5G; R = 3G \)
Rahul is therefore three times as efficient as Gautam.
8R + 6G equals a single work unit.
8R + 2R equals a single work unit.
10R equals one whole work unit.
Rahul's effort in an hour is represented by the fraction R.
It takes 10 hours to complete the task since 10R = 1 R on its own.