To solve the problem, we need to find how many days 3 men will take to complete the job if one man can complete it in 12 days, assuming they work at the same rate.
- Work Rate: If one man completes the job in 12 days, his 1 day work is \( \frac{1}{12} \).
- Combined Work: When multiple men work together, their work rates add up.
- Total Time: The reciprocal of the combined daily work rate.
- One man's time = 12 days
- Number of men = 3
- One man's 1 day work = \( \frac{1}{12} \)
- Three men's 1 day work = \( 3 \times \frac{1}{12} = \frac{3}{12} = \frac{1}{4} \)
- Time taken by 3 men = \( \frac{1}{\frac{1}{4}} = 4 \) days
Three men will complete the job in 4 days.
Match List I with List II:
Choose the correct answer from the options given below:
If a heterozygous tall plant (Tt) is crossed with a dwarf plant (tt), what will be the phenotypic ratio of the offspring?