Question:

If 8 men can complete a work in 12 days, how many days will it take for 4 men to complete the same work?

Show Hint

When the number of workers decreases, the time to complete the work increases in inverse proportion.
Updated On: Jun 6, 2025
  • 24 days
  • 32 days
  • 48 days
  • 96 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Step 1: Understand the relationship between workers and time.
The number of workers and the time taken to complete a job are inversely proportional. This means that if the number of workers decreases, the time to complete the work increases.
Step 2: Apply the formula for inverse proportion.
The formula to calculate time when the number of workers changes is: \[ \text{Time} = \frac{\text{Initial number of men} \times \text{Initial time}}{\text{New number of men}} \] In this case, we have: \[ \text{Time} = \frac{8 \times 12}{4} = 24 \text{ days}. \]
Step 3: Conclusion.
Therefore, 4 men will take 24 days to complete the same work.
Was this answer helpful?
0
0

TS LAWCET Notification