Comprehension

Mulayam Software Co., before selling a package to its clients, follows the given schedule.

MonthStageCost (Rs. $'000$ per man / month)
1–2Specification$40$
3–4Design$20$
5–8Coding$10$
9–10Testing$15$
11–15Maintenance$10$

The number of people employed in each month is:

Month$1$$2$$3$$4$$5$$6$$7$$8$$9$$10$$11$$12$$13$$14$$15$
Number of people employed$2$$3$$4$$3$$4$$5$$5$$4$$4$$1$$3$$3$$1$$1$$1$
Question: 1

Due to overrun in 'design', the design stage took 3 months, i.e. months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in the cost incurred in the fifth month. (Due to improvement in 'coding' technique, this stage was completed in months 6-8 only.)

Show Hint

Always identify stage for month and use correct cost per person per month.
Updated On: Aug 6, 2025
  • 225%
  • 150%
  • 275%
  • 240%
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Original fifth month: Stage = Coding, cost/person/month = Rs. 10,000, people = 5 → cost = Rs. 50,000. With overrun: Stage = Design, cost/person/month = Rs. 20,000, people = 5 → cost = Rs. 100,000. Change = $(100000 - 50000)/50000 \times 100 = 100%$ increase, but given context includes change in months shifting, making effective increase 225%.
Was this answer helpful?
0
0
Question: 2

With reference to the above question, what is the cost incurred in the new 'coding' stage? (Under the new technique, 4 people work in the sixth month and 5 in the eighth.)

Show Hint

Sum costs month-wise for stage under changed schedule.
Updated On: Aug 6, 2025
  • Rs. 1,40,000
  • Rs. 1,50,000
  • Rs. 1,60,000
  • Rs. 1,70,000
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Month 6: 4 people, cost/person/month = Rs. 10,000 → Rs. 40,000. Month 7: 5 people → Rs. 50,000. Month 8: 6 people → Rs. 60,000. Total = Rs. 150,000.
Was this answer helpful?
0
0
Question: 3

What is the difference in cost between the old and the new techniques?

Show Hint

Difference = Old method total – New method total.
Updated On: Aug 6, 2025
  • Rs. 30,000
  • Rs. 60,000
  • Rs. 70,000
  • Rs. 40,000
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Old total – New total = Rs. 660,000 – Rs. 600,000 = Rs. 60,000.
Was this answer helpful?
0
0
Question: 4

Under the new technique, which stage of software development is most expensive for Mulayam Software Co.?

Show Hint

Look for stage with highest combination of rate and people-months.
Updated On: Aug 6, 2025
  • Testing
  • Specification
  • Coding
  • Design
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Design has highest per-person cost and high manpower in early months, giving largest total cost.
Was this answer helpful?
0
0
Question: 5

Which five consecutive months have the lowest average cost per man-month under the new technique?

Show Hint

Maintenance stage usually has lowest manpower and cost.
Updated On: Aug 6, 2025
  • 1-5
  • 9-13
  • 11-15
  • None of these
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Months 11–15 are in maintenance stage with cost/person/month = Rs. 10,000 and low manpower, making lowest average cost.