Let the individual times taken by John, Jack, and Jim to complete the work alone be \( a \), \( b \), and \( c \) days respectively.
Step 1: From equation (1):
\[ a = 2b \]
Step 2: Substitute \( a = 2b \) into equation (2):
\[ \frac{bc}{b + c} = \frac{1}{3}(2b) = \frac{2b}{3} \]
Multiply both sides by \( (b + c) \):
\[ bc = \frac{2b}{3}(b + c) \Rightarrow 3bc = 2b(b + c) \Rightarrow 3c = 2(b + c) \Rightarrow 3c = 2b + 2c \Rightarrow c = 2b \]
Step 3: Now use equation (3):
\[ a - \left( \frac{abc}{ab + bc + ac} \right) = 3 \]
Substitute \( a = 2b \) and \( c = 2b \):
\[ 2b - \left( \frac{2b \cdot b \cdot 2b}{2b \cdot b + b \cdot 2b + 2b \cdot 2b} \right) = 3 \Rightarrow 2b - \left( \frac{4b^3}{2b^2 + 2b^2 + 4b^2} \right) = 3 \Rightarrow 2b - \left( \frac{4b^3}{8b^2} \right) = 3 \Rightarrow 2b - \frac{b}{2} = 3 \Rightarrow \frac{4b - b}{2} = 3 \Rightarrow \frac{3b}{2} = 3 \Rightarrow b = 2 \]
Jack takes 2 days, Jim takes 4 days.
Let John’s work rate be \( x \) units/day.
Then, Jack works at twice the rate of John, so his rate is \( 2x \) units/day.
Jim works in such a way that together with Jack, they complete \(\frac{1}{3}\) of the work that John does in a day:
\[ \text{Jack + Jim} = \frac{1}{3} \times \text{John's total work in } (n+3) \text{ days} \]
That implies Jim’s rate = \( x \) units/day (because: Jack does \(2x\), total is \(3x\), so Jim does \(x\)).
So, total rate of all three together = \( x + 2x + x = 4x \) units/day
John alone takes \( n + 3 \) days to finish the work. So, total work = \( x(n+3) \)
Combined, they take \( n \) days to do the same work. So,
\[ x(n + 3) = 4x \cdot n \]
Divide both sides by \( x \):
\[ n + 3 = 4n \Rightarrow 3n = 3 \Rightarrow n = 1 \]
Thus, total work = \( 4x \cdot 1 = 4x \) units
Jim’s rate = \( x \) units/day
So, time taken by Jim alone = \( \frac{4x}{x} = \boxed{4 \text{ days}} \)
When $10^{100}$ is divided by 7, the remainder is ?