Question:

Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is

Updated On: Aug 17, 2024
  • 30
  • 36
  • 70
  • None of Above
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Let's assume W be the total amount of work.
And g and s be the efficiencies of Gautam and Suhani respectively.
According to the question:
\(⇒\) g + s = \(\frac{W}{20}\) (1 day work) ….. (i)

And given that Gautam is doing only 60%: \(\frac{3g}{5}\)
Suhani is doing 150%: \(\frac{3s}{2}\)
Now, using this, we get:

\(⇒\) \(\frac{3g}{5}+\frac{3s}{2}=\frac{W}{20}\) (1 day work)

\(⇒ \)g + s = \(\frac{3g}{5}+\frac{3s}{2}\)

\(⇒\) \(\frac{s}{g}=\frac{4}{5}\)
This implies that Gautam is more efficient person.
By using equation (i) , we get :
\(⇒\) \(g+\frac{4g}{5}=\frac{W}{20}\)

\(⇒\) \(\frac{9}{5}g=\frac{W}{20}\)

\(⇒\) \(g=\frac{W}{36}\)
Therefore, Gautam takes 36 days to finish the given work.
So, the correct option is (B) : 36.

Was this answer helpful?
0
3

Top Questions on Time and Work

View More Questions