Question:

Four men and three women can do a job in 6 days. When 5 men and 6 women work on the same job, the work gets completed in 4 days. How long will 2 women and 3 men take to do the job?

Updated On: Aug 19, 2025
  • 18
  • 10
  • 8.3
  • 12
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

To solve the problem, let's first define the rates at which men and women work. Let the work done by one man in one day be m and the work done by one woman in one day be w.

According to the problem:

  1. Four men and three women complete the job in 6 days. We can express this as:
    \(6(4m + 3w) = 1\).
  2. Five men and six women complete the job in 4 days:
    \(4(5m + 6w) = 1\).

We now have two equations:

  • \(24m + 18w = 1\)
  • \(20m + 24w = 1\)

Let's solve these equations to find m and w.

Rearranging the first equation:

  • \(24m + 18w = 1\)
  • \(4m + 3w = \frac{1}{6}\)

Rearranging the second equation:

  • \(20m + 24w = 1\)
  • \(5m + 6w = \frac{1}{4}\)

Now multiply the first equation by 2 and the second by 1, to eliminate a variable:

  • \(8m + 6w = \frac{2}{6} = \frac{1}{3}\)
  • \(5m + 6w = \frac{1}{4}\)

Subtract the second equation from the first:

  • \((8m + 6w) - (5m + 6w) = \frac{1}{3} - \frac{1}{4}\)
  • \(3m = \frac{1}{3} - \frac{1}{4}\)
  • \(3m = \frac{4}{12} - \frac{3}{12} = \frac{1}{12}\)
  • \(m = \frac{1}{36}\)

Substitute \(m = \frac{1}{36}\) back into \(4m + 3w = \frac{1}{6}\):

  • \(4\left(\frac{1}{36}\right) + 3w = \frac{1}{6}\)
  • \(\frac{4}{36} + 3w = \frac{1}{6}\)
  • \(\frac{1}{9} + 3w = \frac{1}{6}\)
  • \(3w = \frac{1}{6} - \frac{1}{9}\)
  • \(3w = \frac{3}{18} - \frac{2}{18} = \frac{1}{18}\)
  • \(w = \frac{1}{54}\)

With the rates, \(m = \frac{1}{36}\) and \(w = \frac{1}{54}\), calculate the time for 2 women and 3 men to complete the job:

  • Work done by 2 women and 3 men in one day is:
    \(3\left(\frac{1}{36}\right) + 2\left(\frac{1}{54}\right) = \frac{1}{12} + \frac{1}{27}\)
  • Finding a common denominator (108):
    \(\frac{9}{108} + \frac{4}{108} = \frac{13}{108}\)
  • Time taken to finish the job is then the inverse:
    \(\frac{108}{13} \approx 8.3\) days
Time (in days)≈ 8.3

Therefore, 2 women and 3 men will take approximately 8.3 days to complete the job.

Was this answer helpful?
0
0