‘A’ while working 40% more efficiently can complete a piece of work in 25 days and ‘B’ while working 25% more efficiently can complete the same work in 21 days. While working with their original efficiencies ‘A’ and ‘B’ together worked for 9 days, then find the time taken by ‘A’ alone to complete the remaining work with his original efficiency.
Let total amount of work be 525 units Amount of work done by ‘A’ in one day (with increased efficiency) = \(\frac{525}{25}\) = 21 units Original efficiency of ‘A’ = \(\frac{21}{1.40}\) = 15 units per day Amount of work done by ‘B’ in one day (with increased efficiency) = \(\frac{525}{21}\) = 25 units Original efficiency of ‘B’ = \(\frac{25}{1.25}\) = 20 units per day Amount of work completed by ‘A’ and ‘B’ together in 9 days = 35 × 9 = 315 units Remaining work = 525 – 315 = 210 units Desired time = \(\frac{210}{15}\) = 14 days So, the correct option is (B) : 14 days.