Question:

‘A’ while working 40% more efficiently can complete a piece of work in 25 days and ‘B’ while working 25% more efficiently can complete the same work in 21 days. While working with their original efficiencies ‘A’ and ‘B’ together worked for 9 days, then find the time taken by ‘A’ alone to complete the remaining work with his original efficiency.

Updated On: Aug 21, 2024
  • 7 days
  • 14 days
  • 12 days
  • 6 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Let total amount of work be 525 units
Amount of work done by ‘A’ in one day (with increased efficiency) = \(\frac{525}{25}\) = 21 units
Original efficiency of ‘A’ = \(\frac{21}{1.40}\) = 15 units per day
Amount of work done by ‘B’ in one day (with increased efficiency) = \(\frac{525}{21}\) = 25 units
Original efficiency of ‘B’ = \(\frac{25}{1.25}\) = 20 units per day
Amount of work completed by ‘A’ and ‘B’ together in 9 days = 35 × 9 = 315 units
Remaining work = 525 – 315 = 210 units
Desired time = \(\frac{210}{15}\) = 14 days
So, the correct option is (B) : 14 days.
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions