Question:

Which method/technique is used to analyze the tasks involved in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project?

Show Hint

CPM is useful in project management to ensure that the project is completed in the least amount of time while meeting deadlines.
Updated On: Sep 17, 2025
  • Critical Path Method (CPM)
  • Programme Evaluation and Review Technique (PERT)
  • Event Chain methodology
  • Gantt charts
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The Critical Path Method (CPM) is used to identify the critical tasks involved in completing a project, calculate the minimum project duration, and ensure that tasks are completed on time by optimizing task sequencing.