Let the total work required to paint the fence be 1 unit.
Step 1:
Work rates:
- A takes 6 days to paint the fence, so A's rate is \( \frac{1}{6} \) of the work per day.
- B takes 8 days to paint the fence, so B's rate is \( \frac{1}{8} \) of the work per day.
Step 2:
In the first 2 days, A and B work together:
\[
\text{Work done by A and B in 2 days} = 2 \times \left( \frac{1}{6} + \frac{1}{8} \right) = 2 \times \frac{7}{24} = \frac{7}{12}
\]
Step 3:
After 2 days, the remaining work is \( 1 - \frac{7}{12} = \frac{5}{12} \).
Step 4:
C joins A and B. Let C's rate be \( \frac{1}{c} \), where \( c \) is the number of days it takes C to paint the entire fence alone.
Together, A, B, and C's rate is \( \frac{1}{6} + \frac{1}{8} + \frac{1}{c} \).
Step 5:
In the next 1 day, A, B, and C complete the remaining \( \frac{5}{12} \) of the work:
\[
\left( \frac{1}{6} + \frac{1}{8} + \frac{1}{c} \right) \times 1 = \frac{5}{12}
\]
\[
\frac{7}{24} + \frac{1}{c} = \frac{5}{12}
\]
\[
\frac{1}{c} = \frac{5}{12} - \frac{7}{24} = \frac{10}{24} - \frac{7}{24} = \frac{3}{24} = \frac{1}{8}
\]
Step 6:
Thus, \( c = 8 \). Therefore, C can paint the entire fence in 8 days.