In a pipelined system with m stages, the number of clock cycles required to process n tasks is given by the formula:
\[
\text{Total clock cycles} = (n + m - 1)
\]
Where:
- n = 200 (number of tasks)
- m = 6 (number of segments in the pipeline)
Thus, the total clock cycles is:
\[
\text{Total clock cycles} = 200 + 6 - 1 = 205
\]
Therefore, the correct answer is 1. 205.