Comprehension

schedule of four employeesThe figure above shows the schedule of four employees – Abani, Bahni, Danni and Tinni –whom Dhoni supervised in 2020. Altogether there were five projects which started and concluded in 2020 in which they were involved. For each of these projects and for each employee, the starting day was at the beginning of a month and the concluding day was the end of a month, and these are indicated by the left and right end points of the corresponding horizontal bars. The number within each bar indicates the percentage of assigned work completed by the employee for that project, as assessed by Dhoni.
For each employee, his/her total project-month (in 2020) is the sum of the number of months(s)he worked across the five project, while his/her annual completion index is the weightage average of the completion percentage assigned from the different projects, with the weights being the corresponding number of months (s)he worked in these projects. For each project, the total employee-month is the sum of the number of months four employees worked in this project, while its completion index is the weightage average of the completion percentage assigned for the employees who worked in this project, with the weights being the corresponding number of months they worked in this project.

Question: 1

Which of the following statements is/are true?
I: The total project-month was the same for the four employees.
II: The total employee-month was the same for the five projects.

Updated On: Aug 20, 2024
  • Only I
  • Both I and II
  • Only II
  • Neither I nor II
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct answer is (A): Only I

Was this answer helpful?
0
0
Question: 2

Which employees did not work in multiple projects for any of the months in 2020?

Updated On: Aug 20, 2024
  • All four of them
  • Only Tinni
  • Only Abani and Bahni
  • Only Abani, Bahni and Danni
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

The correct answer is (D);
Only Abani, Bahni and Danni
Was this answer helpful?
0
0
Question: 3

The project duration, measured in terms of the number of months, is the time during which at least one employee worked in the project. Which of the following pairs of the projects had the same duration?

Updated On: Aug 20, 2024
  • Project 3, Project 5
  • Project 4, Project 5
  • Project 1, Project 5
  • Project 3, Project 4
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

The correct answer is (D) Project 3, Project 4

Was this answer helpful?
0
0
Question: 4

The list of employees in decreasing order of annual completion index is:

Updated On: Aug 20, 2024
  • Danni, Tinni, Bahni, Abani
  • Danni, Tinni, Abani, Bahni
  • Bahni, Abani, Tinni, Danni
  • Tinni, Danni, Abani, Bahni
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct answer is (B): Danni, Tinni, Abani, Bahni

Was this answer helpful?
0
0

Top Questions on Data Interpretation

View More Questions

Questions Asked in CAT exam

View More Questions