Let's first calculate the rates at which Sam, Mohit, and Ayna work.
Sam's rate = $\frac{1}{20}$ (jobs per day)
Mohit is twice as fast as Sam, so Mohit's rate of work is:
Mohit's rate = $2 \times \frac{1}{20} = \frac{1}{10}$
Ayna is thrice as slow as Mohit, so Ayna's rate of work is:
Ayna's rate = $\frac{1}{3} \times \frac{1}{10} = \frac{1}{30}$
Work done on each day: The work arrangement is as follows:
On the first day, Sam and Mohit work together. The total work done on the first day is:
Work on day 1 = $\frac{1}{20} + \frac{1}{10} = \frac{1+2}{20} = \frac{3}{20}$
On the second day, Sam and Ayna work together. The total work done on the second day is:
Work on day 2 = $\frac{1}{20} + \frac{1}{30} = \frac{3+2}{60} = \frac{5}{60} = \frac{1}{12}$
On the third day, Mohit and Ayna work together. The total work done on the third day is:
Work on day 3 = $\frac{1}{10} + \frac{1}{30} = \frac{3+1}{30} = \frac{4}{30} = \frac{2}{15}$
Total work done in 3 days: The total work done in one complete cycle (3 days) is:
\[ \text{Total work in 3 days} = \frac{3}{20} + \frac{1}{12} + \frac{2}{15} \]
To add these fractions, we need to find the least common denominator (LCD). The LCD of 20, 12, and 15 is 60.
\[ \frac{3}{20} = \frac{9}{60}, \quad \frac{1}{12} = \frac{5}{60}, \quad \frac{2}{15} = \frac{8}{60} \]
Thus, the total work done in one cycle is:
\[ \frac{9}{60} + \frac{5}{60} + \frac{8}{60} = \frac{22}{60} = \frac{11}{30} \]
So, in every 3-day period, $\frac{11}{30}$ of the total work is completed.
Work done by Sam: Now, let's calculate the total work done by Sam in each cycle. Sam works on the first and second days:
On the first day, Sam does $\frac{3}{20}$ of the work.
On the second day, Sam does $\frac{5}{60} = \frac{1}{12}$ of the work.
Thus, the total work done by Sam in one cycle is:
\[ \frac{3}{20} + \frac{1}{12} = \frac{14}{60} = \frac{7}{30} \]
Sam's total work in 3 days = $\frac{3}{20} + \frac{1}{12} = \frac{4}{15} + \frac{1}{12} = \frac{11}{30}$
Fraction of total work done by Sam: The total work done in one cycle is $\frac{11}{30}$. Therefore, the fraction of the total work done by Sam in one cycle is:
\[ \frac{\frac{7}{30}}{\frac{11}{30}} = \frac{7}{11} \]
Thus, the fraction of total work done by Sam is $\frac{7}{11}$. Therefore, the correct answer is Option (2).