Question:

In the spiral model of software development, the primary determinant in selecting activities in each iteration is ________.
 

Show Hint

The Spiral Model is particularly beneficial for projects with significant uncertainty or risk.
Updated On: Jun 16, 2025
  • iteration size
  • cost
  • risk
  • adopted process such as rational unified process or extreme programming
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

In the Spiral Model, risk management is the primary driver for selecting which activities to focus on in each iteration. The model emphasizes risk analysis and mitigation, with each iteration focusing on the risks identified in previous cycles. The cost and iteration size are considered, but they are secondary to addressing the risks associated with the project.
Was this answer helpful?
0
0