Question:

If P, Q and R work together, they take 12 days to complete the work. However, if only P and R work, they take 20 days to complete the work. A schedule is made such that P and R work every day, while Q joins them only on alternate days i.e. on 1st, 3rd, 5th, 7th,… days. On which day will the work be completed?

Updated On: Oct 22, 2024
  • 15th
  • 14th
  • 13th
  • 17th
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct answer is (A),15th
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions