- If P, Q, and R work together, they complete the work in 12 days. Their combined rate of work is:
\[ \text{Combined rate of P, Q, and R} = \frac{1}{12} \text{ work per day} \]
- If only P and R work together, they complete the work in 20 days. Their combined rate of work is:
\[ \text{Combined rate of P and R} = \frac{1}{20} \text{ work per day} \]
- Since P and R complete \(\frac{1}{20}\) of the work each day, we can find Q's rate of work as follows:
\[ \text{Q's rate} = \frac{1}{12} - \frac{1}{20} \]
Finding the LCM of 12 and 20:
\[ \text{Q's rate} = \frac{5}{60} - \frac{3}{60} = \frac{2}{60} = \frac{1}{30} \]
- On alternate days, Q works with P and R, so the rate of work when all three work together is:
\[ \frac{1}{12} \text{ work per day} \]
- On the other days, P and R complete:
\[ \frac{1}{20} \text{ work per day} \]
- The total work done in two days is:
\[ \frac{1}{12} + \frac{1}{20} = \frac{5}{60} + \frac{3}{60} = \frac{8}{60} = \frac{2}{15} \]
- Therefore, in every two-day period, \(\frac{2}{15}\) of the work is completed. To complete the entire work:
\[ \frac{1}{\frac{2}{15}} = 7.5 \text{ two-day periods} \]
Since 7.5 periods correspond to 15 days, the work will be completed on the 15th day.
Conclusion: The correct answer is (a) 15th day.