Question:

A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, then the time taken by B to finish the work is

Updated On: May 17, 2024
  • 12 days
  • 14 days
  • 16 days
  • 18 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct option is (A): 12 days
Was this answer helpful?
0
0