Question:
A set of 5 jobs is to be planned on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs.2 per day.
Job
Processing Time
P
5
Q
2
R
2
S
2
T
1
Schedule that minimizes total inventory cost is:
CUET (PG) - 2023
CUET (PG)
Updated On:
Mar 21, 2024
T-S-Q-R-P
P-Q-R-S-T
T-R-S-Q-P
T-S-R-Q-P
Hide Solution
Verified By Collegedunia
The Correct Option is
A
Solution and Explanation
The correct option is (A): T-S-Q-R-P
Download Solution in PDF
Was this answer helpful?
0
0
Questions Asked in CUET PG exam
What is the one-word synonym for connotation?
CUET (PG) - 2025
Synonyms
View Solution
What is the antonym of eradicate?
CUET (PG) - 2025
Antonyms
View Solution
Who was the first Secretary-General of the UN?
CUET (PG) - 2025
United Nations and its Organizations
View Solution
What is the correct verb form: He, as well as his friends, ?
CUET (PG) - 2025
Verbs
View Solution
Which preposition is correct: Chanakya lived ?
CUET (PG) - 2025
Prepositions
View Solution
View More Questions