Question:
A set of 5 jobs is to be planned on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs.2 per day.
Job
Processing Time
P
5
Q
2
R
2
S
2
T
1
Schedule that minimizes total inventory cost is:
CUET (PG) - 2023
CUET (PG)
Updated On:
Mar 21, 2024
T-S-Q-R-P
P-Q-R-S-T
T-R-S-Q-P
T-S-R-Q-P
Hide Solution
Verified By Collegedunia
The Correct Option is
A
Solution and Explanation
The correct option is (A): T-S-Q-R-P
Download Solution in PDF
Was this answer helpful?
0
0
Questions Asked in CUET PG exam
A bought an article at a certain price and sold it at 10% profit. B bought the same article at a price 10% lesser than A and sold it at ₹18 lesser than A. B's gain percentage in this deal is 20%. At what price B bought the article?
CUET (PG) - 2025
Profit and Loss
View Solution
The traffic lights at three different road crossings change after every 48 seconds, 72 seconds and 108 seconds respectively. If they all change simultaneously at 8:20:00 hours, then at what time will they again change simultaneously?
CUET (PG) - 2025
Quantitative Aptitude
View Solution
In terracotta which materials are mainly used to build strong clay
(A) Grog
(B) Metal
(C) Cotton
(D) Stone
Choose the correct answer from the options given below:
CUET (PG) - 2025
Ceramics and Pottery
View Solution
Under the Protection of Women from Domestic Violence Act, 2005, the definition of "domestic relationship" includes:
CUET (PG) - 2025
Social Legislation
View Solution
The mezzotint method invented by Lindberg Von Sleigen is a version of:
CUET (PG) - 2025
Printmaking Techniques
View Solution
View More Questions