Question:
A set of 5 jobs is to be planned on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs.2 per day.
Job
Processing Time
P
5
Q
2
R
2
S
2
T
1
Schedule that minimizes total inventory cost is:
CUET (PG) - 2023
CUET (PG)
Updated On:
Mar 21, 2024
T-S-Q-R-P
P-Q-R-S-T
T-R-S-Q-P
T-S-R-Q-P
Hide Solution
Verified By Collegedunia
The Correct Option is
A
Solution and Explanation
The correct option is (A): T-S-Q-R-P
Download Solution in PDF
Was this answer helpful?
0
0
Questions Asked in CUET PG exam
Which of the following is a famous historical site that features terracotta statues?
1. Machu Picchu
2. Stonehenge
3. Black Sun
4. Terracotta Army
Choose the correct answer from the options given below:
CUET (PG) - 2025
Ceramics and Pottery
View Solution
Which of the following is the most common use of terracotta?
(A) Paper Product
(B) Sculpture
(C) Electrical components
(D) Machu Picchu
(E) Pottery
Choose the correct answer from the options given below:
CUET (PG) - 2025
Pottery
View Solution
Designs can be made using kaolin and red clay.
(A) Circular
(B) Rectangular
(C) Glaze
(D) Bisque
Choose the correct answer from the options given below:
CUET (PG) - 2025
Ceramics and Pottery
View Solution
'Bottle' and 'Growing Stones' are pottery by artists.
(A) Gurcharan Singh
(B) Ramchandra Shukla
(C) K. V. Jena
(D) P. Daroz
Choose the correct answer from the options given below:
CUET (PG) - 2025
Indian Artistsc
View Solution
Identify the famous pottery artist.
(A) K. V. Jena
(B) D. P. Roy Choudhary
(C) Mansimran Singh
(D) Kawal Krishna
Choose the correct answer from the options given below:
CUET (PG) - 2025
Indian Artistsc
View Solution
View More Questions