Which one of the following divisions is not part of aggregate production planning?
CUET (PG) - 2023
CUET (PG)
Industrial Engineering
Aggregate Production Planning and Scheduling
A set of 5 jobs is to be planned on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs.2 per day.
Job
Processing Time
P
5
Q
2
R
2
S
2
T
1
Schedule that minimizes total inventory cost is: