Question:

A protection system engineer is planning to provide complete protection for a 3-phase transmission line. He can achieve this by:

Show Hint

To fully protect a 3-phase transmission line, you need both phase fault relays and earth fault relays for complete fault detection.
Updated On: May 4, 2025
  • Three phase fault relays and three earth fault relays
  • Three phase fault relays and two earth fault relays
  • Two phase fault relays and two earth fault relays
  • Two phase fault relays and one earth fault relay
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

To provide complete protection for a 3-phase transmission line, the protection system engineer should use:
- Two phase fault relays to protect the line against phase faults, and
- One earth fault relay to protect against ground faults.
This combination ensures that both phase-to-phase and phase-to-ground faults are adequately detected and protected against.
Thus, the correct answer is Two phase fault relays and one earth fault relay.