Question:

A project has six activities and the precedence relationship among them is shown in the table.
ActivityPrecedent activities
ANone
BNone
CNone
DA, B
EB,C
FA, B
The minimum number of dummy activities needed to draw an activity-on-arrow (AOA) representation of the project network is ___ .

Updated On: Jul 12, 2024
  • 0
  • 1
  • 2
  • 3
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

The correct option is (D): 3.