A contractor agreed to build a road in \(200\) days using \(140\) workers.
After \(60\) days, only \(\frac{1}{4}\) of the road was completed.
This means the remaining work is:
\(1 - \frac{1}{4} = \frac{3}{4}\)
The number of days left to complete the remaining work is:
\(200 - 60 = 140\) days
Let \(x\) be the number of extra workers required to complete the remaining work on time.
We will use the formula:
where:
Applying the formula for both phases:
Work done in first 60 days by 140 persons:
Multiply both sides:
Simplifying LHS:
\[140 \times 60 \times 4 = 33600\]
RHS:
Now equate both sides:
Divide both sides by 4:
\[8400 = \frac{1}{3} \times 140 \times (140 + x)\]Multiply both sides by 3:
\[25200 = 140 \times (140 + x)\]Divide both sides by 140:
\[\frac{25200}{140} = 140 + x \Rightarrow 180 = 140 + x\]Therefore,
\[x = 180 - 140 = 40\]So, 40 extra workers are required to finish the work on time.